North Linden 1

Construction Updates: Week of April 22, 2024

Please note that construction schedules are subject to change due to weather, site issues, etc. Reference this MAP to view the impacted construction areas for next week. Unsure about which is your area? Visit the Blueprint- map and type in your address to find out!

Sump pump installations are offered for a limited time only! We have a few spots left on our list! If you are interested, contact us ASAP and we’ll schedule your no-obligation assessment to see if a sump pump is right for you!

General Updates

If you have a basement backup (sewer water coming up from your floor drain), please report this to the City by calling 614-645-7102. Please note that crews are working diligently to investigate issues throughout the city, and so we may not be able to respond immediately. We appreciate your patience and understanding.

Project Status

North Linden 1 Construction Update – Week of April 22, 2024

 

AGLER-BERRELL

Area 1: 2807-2836 Linview Ave. — Sanitary Lateral Lining

Area 2: 22734-2821 Linview Ave. — Downspout Installations

Area 3: 2677-2842 Fern Ave. — Sanitary Lateral Lining

Area 4: 1923 Denune Ave. — Sanitary Lateral Lining

Area 5: 1884-2006 Aberdeen Ave. — Downspout Installations

Area 6: 1922 Minnesota Ave. — Sanitary Lateral Lining

ARTANE-PARKWOOD

NO SCHEDULED WORK

HUDSON-MCGUFFEY

NO SCHEDULED WORK

OAKLAND PARK-MEDINA

Area 7: 1616-1658 Melrose Ave. — Sanitary Lateral Lining

Area 8: 1637-1651 Milford Ave. — Sanitary Lateral Lining

Area 9: 2837-2859 Oaklawn St. — Sanitary Lateral Lining

Area 10: 2840-2864 Bremen St. — Sanitary Lateral Lining

Area 11: Dresden St. — Sidewalk Panel Installations

Area 12: Norwood St. — Sidewalk Panel Installations

Area 13: Medina Ave. — Sidewalk Panel Installations

Area 14: 3036 Dresden St. — Sanitary Lateral Lining

Construction

Design Details

Current Projects

North Linden 1 is bounded by Oakland Park Ave to the north, Berrell Ave. and Parkwood to the east, E. Hudson St. to the south and Medina Ave. and Hamilton Ave. to the west. North Linden 1 is divided into four project areas:

Oakland Park-Medina (Medina Ave. to Cleveland Ave. between Oakland Park and E. Weber Rd.)

Agler-Berrell (Cleveland Ave. to Berrell Ave. between Oakland Park and Genessee Ave.)

Hudson-McGuffey (Hamilton Ave. to Cleveland Ave. between E. Weber Rd. and E. Hudson St.)

Artane-Parkwood (Cleveland Ave. to Parkwood Ave. between Genessee Ave. to E. Hudson St.)

Linview Park –Preconstruction Meeting Recording

Total Suspended Solids (TSS) Basins – Preconstruction meeting January 2022

Linden Project Area Map

North Linden 1 Project Schedule

Phase 1

Surveying: 2015-2017

Surveyors are in the neighborhood to document water flow patterns, topography, existing utilities, and other residential infrastructure, such as downspouts.

Phase 2

Green Infrastructure Design: 2020-2022

The engineering team identifies the types and locations of green infrastructure that will meet the needs of the neighborhood. During the design phase, we seek resident feedback through surveys, public meetings, and field visits.

Learn More

Phase 3

Shovels in the Ground: 2021-2022

Construction of green infrastructure involves work in the public right-of-way and street. All neighborhood residents will be notified of anticipated impacts, and Blueprint will send out weekly construction updates to keep everyone informed of the schedule and activities.

Learn More

Green Infrastructure Construction: 2021

Rain gardens and permeable pavement sites are installed. During this time other city infrastructure work may occur, such as waterline upgrades or sidewalk installations.

Lateral Lining and Roofwater Redirection: 2022-2025

Individual homes are assessed for lateral lining and roofwater redirection. These drainage improvements prevent stormwater from entering the sanitary sewer lines by getting that water away from your home and out to the street, so it can drain to the storm sewer system

Project Milestones & Events

Preliminary Design Meeting

April 10, 2017

Meeting Recap

Detailed Design Meeting

March 14, 2018

Meeting Recap

Final Design

June 18, 2020

Meeting Recap

Pre-Construction Meeting

 

Meeting Recap

See What’s Planned

Green Infrastructure Locations & Designs

See where green infrastructure is planned in your neighborhood.

Oakland Park – Medina

Agler – Berrell

Artane – Parkwood

Hudson – McGuffey

Do you have a community meeting or event you would like Blueprint to attend? We’d love to be there!

Latest Updates

Keep up on the latest announcements in your neighborhood! Sign up for email or text notifications to make sure you stay informed.

Top