Blueprint Miller Kelton

Miller Kelton, also known as Driving Park, has been identified as a Blueprint priority area due to a significant number of basement backup incidences and the sanitary sewer overflow that discharges into Alum Creek near the Alum Creek Multi-Use Trail. Though a portion of this area is served by a separate, combined sewer system, over 3 acres of storm water runoff drain to the sanitary sewer system, creating additional capacity issues and leading to basement backups.

Newton Bedford: Active Construction!

Design Details

Current Projects

Miller Kelton is bounded by Mooberry and E. Main St. to the north, S. Nelson Rd. to the east, E. Livingston Avenue to the south and S. 18th St. to the west.

Miller-Kelton is divided into two project areas:

Newton-Bedford: S. 18th St. to Miller Ave., between Mooberry and E. Livingston Ave.

Kent-Fairwood: Miller Ave. to S. Nelson Rd., between E. Main St. and E. Livingston Ave.

Project Map

Miller-Kelton Permeable Pavement Schedule

2026

All of Carpenter

Waterline: May 2026 to July 2026

Roadway Work: July 2026 to October 2026

Restoration: August 2026 to September 2026

22nd street

All waterline work: May 2026 to August 2026

22nd Street, Block 1: Newton to Carrol Alley

     -Roadway Work: August 2026 to November 2026

     -Restoration: September 2026 to October 2026

All of Kimball

Waterline: June 2026 to August 2026

Roadway Work: July 2026 to November 2026

Restoration: August 2026 to October 2026

2027

Block 2 of 22nd

22nd Street, Block 2: Carrol Alley to Mooberry

     -Waterline: Completed in 2026

     -Roadway Work: July 2027 to October 2027

     -Restoration: August 2027 to September 2027

Linwood – South

Linwood – Block 1: Livingston to Newton

     -Waterline: October 2026 to November 2026

     -Roadway Work: March 2027 to July 2027

     -Restoration: April 2027 to June 2027

Linwood – North

Linwood – Block 2: Newton to Mooberry

     -Waterline: October 2026 to November 2026

     -Roadway Work: July 2027 to October 2027

     -Restoration: August 2027 to September 2027

Miller-Kelton Project Schedule

Phase 1

Surveying: 2019-2025

Surveyors are in the neighborhood to document water flow patterns, topography, existing utilities, and other residential infrastructure, such as downspouts.

Phase 2

Green Infrastructure Design: 2018-2026

The engineering team identifies the types and locations of green infrastructure that will meet the needs of the neighborhood. During the design phase, we seek resident feedback through surveys, public meetings, and field visits.

Learn More See What’s Planned

Phase 3

Shovels in the Ground: 2026-2027

Construction of green infrastructure involves work in the public right-of-way and street. All neighborhood residents will be notified of anticipated impacts, and Blueprint will send out weekly construction updates to keep everyone informed of the schedule and activities.

Learn More

Green Infrastructure Construction: 2026-2027

Rain gardens and porous pavement sites are installed. During this time other city infrastructure work may occur, such as waterline upgrades, lead service line removal or sidewalk installations.

Lateral Lining: 2026-2028

Individual homes are assessed for lateral lining and roofwater redirection. These home improvements prevent stormwater from entering the sanitary sewer lines by getting that water away from your home and out to the street, so it can drain to the storm sewer system

Sump Pumps: 2026-2028

All homes in the project area are eligible to receive a sump pump if residents do not have one, or if the current pump is in disrepair. Visit our sump pump project page to learn more.

Roofwater Redirection: 2030-2033

Individual homes are assessed for lateral lining and roofwater redirection. These home improvements prevent stormwater from entering the sanitary sewer lines by getting that water away from your home and out to the street, so it can drain to the storm sewer system

Project Milestones & Events

Preliminary Design Meeting

May 22, 2018

Meeting Recap

Detailed Design Meeting

October 15, 2019

Meeting Recap

Final Design Meeting

August 10, 2021

 

Meeting Recap

Pre-Construction Meeting

May 6, 2026

Public Meeting Presentation

See What’s Planned

Green Infrastructure Locations

See where green infrastructure is planned in your neighborhood.

Newton-Bedford

Kelton-Fairwood

Do you have a community meeting or event you would like Blueprint to attend? We’d love to be there!

Latest Updates

Keep up on the latest announcements in your neighborhood! Sign up for email or text notifications to make sure you stay informed.

Top