Sunrise-Glenn Construction Update – Week of September 30, 2024
Reference this MAP to view the impacted construction areas.
Area 1: Basin, curb and sidewalk work — W 6th Ave & Broadview (9/30 – 10/11)
Area 2: Basin, planter & sidewalk work — Wyandotte, Elmwood, and Ashland (10/1 – 10/11)
Area 3: Basin excavation & planter work — W 6th Ave between Grandview & Northwest Blvd (9/30 – 10/11)
Area 4: Basin & planter work — W 7th Ave (10/1 – 10/4)
Area 5: Install fire hydrants — Fairview Ave (10/3 – 10/8)
NOTE: Limited Lane/Street Closures are possible.
Concrete sidewalk replacement to be performed as needed to maintain pedestrian traffic. Continuation of waterline shuts to perform pavement replacement as needed to maintain traffic. If there is any impact on water service, affected individuals will receive advance notice and relevant information directly. To minimize the impact of daytime water service loss, some work may be conducted at night.