Sunrise-Glenn Construction Update – July 29- August 9, 2024
Reference this MAP to view the impacted construction areas.
Area 1: 7/27 – Complete Storm Sewer Install on Wyandotte Ave
Area 2: 7/29 – Perform Waterline Lowerings on King Ave
Area 3: 7/30-8/2: Install Manholes on King Ave
Area 4: 8/5-8/6 – Install Storm Pipes and Perform Water Service Lowering on King Ave
Area 5: 8/8 – Install Manholes on Ashland Ave
Area 6: 8/9 – Install Manhole on Broadview Ave
Note: If there is any impact on water service, affected individuals will receive advance notice and relevant information directly. To minimize the impact of daytime water service loss, some work may be conducted at night. Limited Lane/Street Closures are possible. Pavement replacement will be performed quickly after pipe has been installed, as close to every other day as feasible but road plates will be used until pavement replacement is performed.