Construction Updates: October 5, 2026

Please note that construction schedules are subject to change due to weather, site issues, etc. Reference this MAP to view the impacted construction areas and details for next week.

Unsure about which is your area? Visit the Blueprint- map and type in your address to find out!

Project Status

WALHALLA RAVINE STREAM RESTORATION – CONSTRUCTION UPDATES COMING SOON

Reference this MAP to view the impacted construction areas and details for next week.

***All scheduled work subject to local weather conditions***

  • Construction and road closure begins October 5
  • Tree removal begins October 6, 2026

Active Construction

Construction begins October 5!

Walhalla Design Update

New for 2026: Stream restoration is set to begin October 5! This long-anticipated project will help reduce pollution entering our waterways while sustainably securing the banks of the Walhalla Ravine on the eastern side near Clinton Hts. Ave. 

 

Project information: The roadway material will be asphalt, with no added sidewalk (see final renderings below). This decision was based on community and resident feedback that overwhelmingly supported asphalt material, due to noise and long-term maintenance concerns. The guardrail material is timber on the roadside and reinforced in the back by weathered steel. Upon installation, it will appear shiny silver and, over time, will change to match the color of the wood.

Walhalla Stream Restoration is a Win-Win

Stream restoration in the Walhalla Ravine helps to preserve one of the city’s natural resources and helps to improve water quality by reducing Total Suspended Solids (TSS), which include sediment and various pollutants, from entering the stream due to bank erosion. By restoring banks on Walhalla Ravine, sediment is prevented from entering the Olentangy River downstream. By doing this stream restoration, the Blueprint project saves over $25 million and requires less green infrastructure to be built throughout the Clintonville 3 Blueprint project area.

2024 Project Renderings 

Click Here to View the Presentation Slides!

After feedback received during the February 28, 2024 public meeting, as well as multiple conversations with residents adjacent to the ravine, the final design will include an asphalt roadway with no additional sidewalk. The renderings below show the final designs selected.

 

Walhalla Project Schedule

Phase 1

Surveying: 2017-2018

8 permanent cross sections of the Walhalla Ravine were studied from June 2018 to October 2020. Results of this study indicated that Reach 1 and Reach 2 experienced the highest bank erosion rates, and the restoration of these sections would help Blueprint meet its TSS reduction goal. More information can be found here

Phase 2

Green Infrastructure Design: 2017-2025

After the Walhalla Ravine Study, Stantec developed preliminary plans for the Walhalla Ravine, which were communicated to impacted residents, FLOW, and FOTR. Input from residents, stakeholders, and other city departments further shaped these plans as the team developed the preferred design. This revised detailed design was presented to the community on October 11, 2023 and again on February 28, 2024. Stantec continues to incorporate feedback into this design as they make their way to final design.

Learn More

Phase 3

Shovels in the Ground: Oct. 2026

Construction of green infrastructure involves work in the public right-of-way and street. All neighborhood residents will be notified of anticipated impacts, and Blueprint will send out weekly construction updates to keep everyone informed of the schedule and activities.

Learn More

Frequently Asked Questions

How many trees are being removed from the ravine?

There are currently 14 trees slated for removal 8-inch diameter or larger. Tree removal begins October 6, 2026.

Will the City close Walhalla Road?

The ravine will be closed to pedestrians and vehicles in the project ​
area between Clinton Heights and Longview Ave for the duration of ​
the project, beginning October 5, 2026.

Why does a guardrail have to be installed along the stream?

The guardrail is necessary to uphold City and state standards for pedestrian and vehicle safety.

Why is only this portion of the ravine undergoing restoration work?

The ravine was studied with a comprehensive approach, and this is the section in most need of bank stabilization and stream restoration; restoring this stretch of the ravine aligns with Blueprint project goals.

Project Milestones: Community Touch Points

  • September 10, 2026: Construction Kickoff Meeting!

  • June 26, 2025: Wahalla Project Update Meeting

  • February 28, 2024: Walhalla Detailed Design Meeting

  • October 11, 2023: Walhalla Revised 60% Community Meeting

  • August 8, 2023: Walhalla Impacted Residents Revised Detailed Design Meeting

  • October 26, 2022: Walhalla Ravine Onsite Meeting with DPU leadership

  • October 10, 2022: Walhalla Ravine Detailed Design Meeting

  • October 2022: Impacted Resident Site Visits

  • June 8, 2022: FLOW Science Committee Meeting

  • November 24, 2021: Meeting with FLOW

  • September 21, 2021: Walhalla Ravine Resident Meeting (Impacted Residents)

  • August 20, 2021: Conversation with Friends of the Ravines and Walhalla Ravine Association

 

Top