The Near East is located within one singular project area and is located in a dense urban neighborhood directly south of the South Linden project area.

Surveying Starts 2036

Design Details

Current Projects

Surveying starts in 2036. More information will be available then!

Near East Project Schedule

Phase 1

Surveying: 2036-2038

Surveyors are in the neighborhood to document water flow patterns, topography, existing utilities, and other residential infrastructure, such as downspouts.

Phase 2

Green Infrastructure Design: 2036-2038

The engineering team identifies the types and locations of green infrastructure that will meet the needs of the neighborhood. During the design phase, we seek resident feedback through surveys, public meetings, and field visits.

Learn More See What’s Planned

Phase 3

Shovels in the Ground: 2039

Construction of green infrastructure involves work in the public right-of-way and street. All neighborhood residents will be notified of anticipated impacts, and Blueprint will send out weekly construction updates to keep everyone informed of the schedule and activities.

Learn More

Green Infrastructure Construction: 2036-2043

Rain gardens and porous pavement sites are installed. During this time other city infrastructure work may occur, such as waterline upgrades or sidewalk installations.

Mainline Lining: 2034-2037

This mainline lining (work to seal the main sewer lines on your streets) directly reduces water infiltration and inflow (I/I) into sanitary sewers. Over time, pipes can develop cracks and leaks, allowing rainwater to enter sanitary sewers, filling them beyond their capacity. Overwhelming the system can create a sewage overflow into rivers or back-ups into basements. The lining process quickly replaces an old pipe with minimal impact within the construction area.

Lateral Lining: 2038-2040

Individual homes are assessed for lateral lining and roofwater redirection. These home improvements prevent stormwater from entering the sanitary sewer lines by getting that water away from your home and out to the street, so it can drain to the storm sewer system

Sump Pumps: 2038-2040

All homes in the project area are eligible to receive a sump pump if residents do not have one, or if the current pump is in disrepair. Visit our sump pump project page to learn more.

Roofwater Redirection: 2042-2045

Individual homes are assessed for lateral lining and roofwater redirection. These home improvements prevent stormwater from entering the sanitary sewer lines by getting that water away from your home and out to the street, so it can drain to the storm sewer system

Project Milestones & Events

Preliminary Design Meeting

2037

More to Come!

Detailed Design Meeting

2038

More to Come!

Final Design

2038

More to Come!

Pre-Construction Meeting

2039

More to Come!