Blueprint Hilltop 1

Hilltop has been identified as a Blueprint priority area due to a significant number of basement backup incidences and the sanitary sewer overflow that discharges into Forest Creek/Scioto Big Run. In addition to the four pillars of Blueprint, Hilltop Blueprint includes additional sewer upgrades to address existing deficiencies and severe flooding locations.

Construction Begins 2023

Design Details

Current Projects

Hilltop 1 is bounded by West Broad Street to the north, Wheatland Avenue to the east, Sullivant Avenue to the south and Derrer Road to the west. Hilltop 1 is divided into two project areas:

Eureka-Fremont (S Hague to S Wheatland)

Palmetto-Westgate (Derrer to S Hague)

Project Map

 

Hilltop 1 Construction Update for the week of September 2, 2024

Palmetto-Westgate Green Infrastructure

Construction Activities

  • Road restoration is tentatively scheduled for the first or second week of September for the following locations:
    • Guernsey Avenue and Palmetto Street intersection
    • Crescent Drive and S Roys Avenue intersection
  • Landscape seeding and restoration for the remaining project areas is scheduled for 9/3.

Traffic Impacts

  • One-lane two-way traffic will be maintained with flaggers, as needed.
Eureka-Fremont Green Infrastructure

Construction Activities

  • Contractor is mobilizing equipment and material to the project site on Friday 9/6/24. Work is scheduled to begin the following week and additional details will be provided with next week’s update.

Traffic Impacts

    • No traffic impacts are anticipated with mobilization next week.

Click HERE to see impacted area.

 

Hilltop 1 Project Schedule

Phase 1

Surveying: 2016-2018

Surveyors are in the neighborhood to document water flow patterns, topography, existing utilities, and other residential infrastructure, such as downspouts.

Phase 2

Green Infrastructure Design: 2018-2021

The engineering team identifies the types and locations of green infrastructure that will meet the needs of the neighborhood. During the design phase, we seek resident feedback through surveys, public meetings, and field visits.

Learn More

 

Phase 3

Shovels in the Ground: 2023-2024

Construction of green infrastructure involves work in the public right-of-way and street. All neighborhood residents will be notified of anticipated impacts, and Blueprint will send out weekly construction updates to keep everyone informed of the schedule and activities.

Learn More

Green Infrastructure Construction: 2023

Rain gardens and porous pavement sites are installed. During this time other city infrastructure work may occur, such as waterline upgrades or sidewalk installations.

Lateral Lining and Roofwater Redirection: 2024

Individual homes are assessed for lateral lining and roofwater redirection. These home improvements prevent stormwater from entering the sanitary sewer lines by getting that water away from your home and out to the street, so it can drain to the storm sewer system

Project Milestones & Events

Preliminary Design Meeting

June 6, 2018

Meeting Recap

Detailed Design Meeting

10/9 & 10/10 2019

Meeting Recap

Final Design Meeting

June 23, 2021

Meeting Recap

Pre-Construction Meeting

July 18, 2023

Palmetto-Westgate
Event Presentation

Pre-Construction Meeting

August 15, 2024

Eureka-Fremont
Event Presentation

See What’s Planned

Green Infrastructure Locations

See where green infrastructure is planned in your neighborhood.

Hilltop 1 Eureka Fremont

Hilltop 1 Palmetto Westgate

Do you have a community meeting or event you would like Blueprint to attend? We’d love to be there!

Latest Updates

Keep up on the latest announcements in your neighborhood! Sign up for email or text notifications to make sure you stay informed.

Top