Construction Updates: Week of September 21, 2026

Please note that construction schedules are subject to change due to weather, site issues, etc.

Unsure about which is your area? Visit the Blueprint- map and type in your address to find out!

Eureka Fremont

Integrated Solution, Permeable Pavers, Waterline Improvements, & Resurfacing

  • Tree plantings, asphalt resurfacing, concrete restoration, and site clean up across the project area
  • Temporary lane closures with flaggers/detours as needed

Lateral Lining Project 5

  • Lateral cleaning and sanitary point repairs throughout the project area
    • Limited access through alleys. Residents will be notified in advance of the lateral lining work.

Eureka/Fremont Lateral Lining Project 6

  • Lateral cleaning and sanitary point repairs throughout the project area
    • Limited access through alleys. Residents will be notified in advance of the lateral lining work.

Palmetto Westgate

Palmetto/Westgate Lateral Lining Project 1

  • Lateral lining, Vac A Tee, and cleanout installations throughout the project area  
    • Limited access through alleys. Residents will be notified in advance of cleanout installations and lateral lining work.

Palmetto/Westgate Lateral Lining Project 2

    • Lateral locating, cleaning and CCTV inspections throughout the project area
      • Limited access through alleys. Residents will be notified in advance of cleanout installations and lateral lining work.

Blueprint Hilltop 1

Hilltop has been identified as a Blueprint priority area due to a significant number of basement backup incidences and the sanitary sewer overflow that discharges into Forest Creek/Scioto Big Run. In addition to the four pillars of Blueprint, Hilltop Blueprint includes additional sewer upgrades to address existing deficiencies and severe flooding locations.

NEW for 2026! Permeable Pavers on the way for Palmetto Westgate: Permeable paver construction begins August 26, 2026! 

Active Construction!

Design Details

Current Projects

Hilltop 1 is bounded by West Broad Street to the north, Wheatland Avenue to the east, Sullivant Avenue to the south and Derrer Road to the west. Hilltop 1 is divided into two project areas:

Eureka-Fremont (S Hague to S Wheatland)

Palmetto-Westgate (Derrer to S Hague)

Project Map

 

Hilltop 1 Project Schedule

Phase 1

Surveying: 2016-2018

Surveyors are in the neighborhood to document water flow patterns, topography, existing utilities, and other residential infrastructure, such as downspouts.

Phase 2

Green Infrastructure Design: 2018-2021

The engineering team identifies the types and locations of green infrastructure that will meet the needs of the neighborhood. During the design phase, we seek resident feedback through surveys, public meetings, and field visits.

Learn More

 

Phase 3

Shovels in the Ground: 2026-2027

Construction of green infrastructure involves work in the public right-of-way and street. All neighborhood residents will be notified of anticipated impacts, and Blueprint will send out weekly construction updates to keep everyone informed of the schedule and activities.

Learn More

Green Infrastructure Construction: 2026-2027

Rain gardens and porous pavement sites are installed. During this time other city infrastructure work may occur, such as waterline upgrades or sidewalk installations.

Lateral Lining: 2026-2028

Individual homes are assessed for lateral lining. These home improvements prevent stormwater from entering the sanitary sewer lines by getting that water away from your home and out to the street, so it can drain to the storm sewer system

Sump Pumps: 2026-2028

All homes in the project area are eligible to receive a sump pump if residents do not have one, or if the current pump is in disrepair. Visit our sump pump project page to learn more.

Project Milestones & Events

Preliminary Design Meeting

June 6, 2018

Meeting Recap

Detailed Design Meeting

10/9 & 10/10 2019

Meeting Recap

Final Design Meeting

June 23, 2021

Meeting Recap

Pre-Construction Meeting

July 18, 2023

Palmetto-Westgate
Event Presentation

Pre-Construction Meeting

August 15, 2024

Eureka-Fremont
Event Presentation

See What’s Planned

Green Infrastructure Locations

See where green infrastructure is planned in your neighborhood.

Hilltop 1 Eureka Fremont

Hilltop 1 Palmetto Westgate

Do you have a community meeting or event you would like Blueprint to attend? We’d love to be there!

Latest Updates

Keep up on the latest announcements in your neighborhood! Sign up for email or text notifications to make sure you stay informed.

Top