Please note that construction schedules are subject to change due to weather, site issues, etc.

Reference this Construction MAP to view the impacted construction areas for next week.

Unsure about which is your area? Visit the Blueprint map and type in your address to find out!

General Updates

  • The Department of Public Service reports that progress on reconstruction and paving of some Clintonville streets has been disrupted early by cold, wet weather. This has pushed completion of the streets into the 2019 construction season. The streets will be maintained to be passable and usable this winter.
  • Inlet protections for storm sewer inlets will remain during active construction. Please do not tamper with or remove them, they are required construction site controls to keep sediment and debris from the construction activities out of the storm sewer. Newly constructed rain garden inlets are also initially blocked with straw waddles to allow the plants to get established and stabilized before becoming fully functional.
  • The rain gardens are designed to drain in 48 hours or less. Some standing water within the garden after a rain event is normal. However, if the rain gardens are overflowing or have standing water for more than 2 days, please report that to blueprint@columbus.gov.
  • Just like a normal storm drain, the rain gardens can’t do their job if leaves are piling up and blocking water from entering the inlet. Our crews will clear these inlets during regular maintenance, but if you see leaves piling up and blocking the rain garden inlets, feel free to push them aside to allow rain water to enter. And, as always, remember to keep leaves and yard waste out of the streets as much as possible.

 

Schreyer Springs

  • Facemyer will be onsite regularly to maintain the rain gardens and will be completing the additional stone walls to the rain gardens on Eastlea Dr. the first half of the week. Once they finish the remaining walls early next week they will continue to work on Schreyer Pl until complete.
  • Facemyer is near the end of the stone wall additions and project being done by end of March, weather dependent.  Sod will be placed, and final restoration will begin the first week of May. Residents who will be impacted by this work have been contacted. All work is weather dependent, and the schedule will be adjusted accordingly.
  • The steal edging around the rain gardens will be upgraded to aluminum this spring to alleviate any rusting concerns.
  • Private property investigations for downspout redirection and lateral lining for this area will begin Spring 2019. Residents will receive a letter when this area is “activated”.

 

Weisheimer Indian Springs

  • Igel will return late March/early April to continue scheduling home owner appointments and to begin installations of the new downspouts.
  • BLD, the crew conducting the lateral line work will be lining the laterals on Sellers, Desantis, Weisheimer and Village Dr.
    • BLD, will begin prep work on Indian Springs

Blenheim Glencoe

  • The rain gardens and plantings are now complete. Eramo, will be onsite to review the area to evaluate what additional work will take place during the restoration phase. Restoration of the area will begin late March-early April, weather dependent.
  • Eramo will be completing the waterline installation on Dunedin Rd.
  • Late March, Eramo will have their subcontractor Newcomer onsite to make all sidewalk repairs on Torrence and Dunedin
    • Newcomer, will also be working on repairing driveways and ramps on Dunedin later this March as well
    • Once Newcomer has completed their work Strawser will follow behind them to begin paving Torrence, Dunedin and Foster and Sharon where the rain garden modifications took place
  • Additional evaluations of curbs are being conducted in conjunction with repaving plans.
  • Private property investigations for downspout redirection and lateral lining for this area will begin Summer 2019. Residents will receive a letter when this area is “activated”.

Overbrook Chatham

  • There will be no crews working in this area.
  • Reflectors/Delineators will be placed on the bump outs to aid in night-time visibility.
  • Private property investigations for downspout redirection and lateral lining for this area will begin in late March. Residents will receive a letter with more information in the next few weeks.

Cooke Glenmont

  • Private property investigations for downspout redirection and lateral lining for this area will begin in late March. Residents will receive a letter with more information in the next few weeks.

Morse Dominion

  • Shelly & Sands will be onsite working on the below items
    • Rain garden installation on E. Jeffery Pl
    • Rain garden installation on E. Royal Forest Blvd
    • Beginning the punch list items for the entire project area
  • BLD, the crew that is conducting the lateral lining and inspections will be conducting lining in the alley between E. Jeffrey Pl and E. Royal Forest Blvd
  • OBA will be conducting investigations/homeowner meetings on Colerain for the downspout redirection phase of the project, weather dependent. Installations will take place this week starting on E. Dominion Blvd.

Please contact 614-645-1253 or blueprint@columbus.gov with any questions you may have. If you have an emergency, please call 614-645-8276 for Water or 614-645-7102 for Sewers.  

Sump Pump inspections are being conducted in all Clintonville areas. Contact our outreach team if you are interested in learning more about our free sump pump program!