Please note that construction schedules are subject to change due to weather, site issues, etc.

Reference this Construction MAP to view the impacted construction areas for next week.

Unsure about which is your area? Visit the Blueprint map and type in your address to find out!

General Updates

  • The Department of Public Service reports that progress on reconstruction and paving of some Clintonville streets has been disrupted early by cold, wet weather. This has pushed completion of the streets into the 2019 construction season. The streets will be maintained to be passable and usable this winter.
  • Inlet protections for storm sewer inlets will remain during active construction. Please do not tamper with or remove them, they are required construction site controls to keep sediment and debris from the construction activities out of the storm sewer. Newly constructed rain garden inlets are also initially blocked with straw waddles to allow the plants to get established and stabilized before becoming fully functional.
  • The rain gardens are designed to drain in 48 hours or less. Some standing water within the garden after a rain event is normal. However, if the rain gardens are overflowing or have standing water for more than 2 days, please report that to blueprint@columbus.gov.
  • Just like a normal storm drain, the rain gardens can’t do their job if leaves are piling up and blocking water from entering the inlet. Our crews will clear these inlets during regular maintenance, but if you see leaves piling up and blocking the rain garden inlets, feel free to push them aside to allow rain water to enter. And, as always, remember to keep leaves and yard waste out of the streets as much as possible.

 

Schreyer Springs

  • Facemyer will be onsite regularly to maintain the rain gardens and will be installing additional stone walls to the rain gardens on Fairoaks Dr.
  • Facemyer will continue street by street installing the additional stone walls to the rain gardens until Spring 2019. The next street will be Lawnview.  Sod will be placed, and final restoration will occur in Spring of 2019. Residents who will be impacted by this work have been contacted. All work is weather dependent, and the schedule will be adjusted accordingly.
  • Private property investigations for downspout redirection and lateral lining for this area will begin Spring 2019. Residents will receive a letter when this area is “activated”.

Weisheimer Indian Springs

  • Igel will not be onsite next week.
  • BLD, the crew conducting the lateral line work will not be onsite next week.

 

Blenheim Glencoe

  • The rain gardens and plantings are now complete.
  • Crew 1 has completed the water main on E. Torrence.  They will be removing the old fire hydrants and then removing all equipment and steel plates. The site will be cleaned up as weather conditions allow.
  • Crew 1 will be completing items on their punch list for a week then leaving the site. The crew will be back in late March to complete restoration work.
  • Crew 2 will continue working on the waterline on Dunedin.
  • Additional evaluations of curbs are being conducted in conjunction with repaving plans.
  • Private property investigations for downspout redirection and lateral lining for this area will begin Summer 2019. Residents will receive a letter when this area is “activated”.

Overbrook Chatham

  • There will be no crews working in this area.
  • Reflectors/Delineators will be placed on the bump outs to aid in night-time visibility.
  • Private property investigations for downspout redirection and lateral lining for this area will begin early 2019. Residents will receive a letter when this area is “activated”.

Cooke Glenmont

  • Private property investigations for downspout redirection and lateral lining for this area will begin early 2019. Residents will receive a letter when this area is “activated”.

Morse Dominion

  • Shelly & Sands will not be on site next week.
  • BLD, the crew that is conducting the lateral lining and inspections will be onsite cleaning laterals in the alley between Morse and E. Jeffery Pl.
  • OBA will be conducting investigations on E. Jeffery Pl. and Morse Rd. for the downspout redirection phase of the project, weather dependent.

 

Please contact 614-645-1253 or blueprint@columbus.gov with any questions you may have. If you have an emergency, please call 614-645-8276 for Water or 614-645-7102 for Sewers.  

Sump Pump inspections are being conducted in all Clintonville areas. Contact our outreach team if you are interested in learning more about our free sump pump program!